Back to project archive

Construction visualization / planning explanation

Soil Compaction Methods

A visual comparison of three soil-compaction methods and the resources, sequence, and time each required.

Role3D modeling, process visualization, rendering, compositing
Tools3DS Max, V-Ray, After Effects
ContextPre-funding project explanation
DeliverableMethod comparison animation
Case study

Showing what each construction method required.

Before funding the project, stakeholders needed to understand three methods for excavation and controlled compacted fill. Each option involved different equipment, material movement, staging, and time.

I modeled and rendered the sequences in 3DS Max and V-Ray, then composed them in After Effects. By showing the operational differences, the visuals gave the funding discussion a concrete basis.

Next project

Formax Tank Crash

View next